LATESTSSC CGL 2026 Notification Live | ISRO Scientist 'SC' Interview Shortlists Out | NIC Scientist B Active
InterviewJobs.in
Quantitative Aptitude
Importance Rating:★★★★★

Time, Work & Pipes/Cisterns

Ditch the classical fraction method (1/x + 1/y). The LCM Unitary method assumes the total work to be the LCM of given days, turning fractions into small whole-number efficiencies.

Exam Frequency: 2 to 4 questions across all IT and Bank recruitment exams

Essential Formulas & Shortcut Rules

Total Work = Time Taken × Worker Efficiency (Units/day)

The fundamental relationship connecting output and rate.

Work Done = (M₁ × D₁ × H₁ × E₁) / W₁ = (M₂ × D₂ × H₂ × E₂) / W₂

Men-Days-Hours formula for group work scaling.

Net Filling Rate = Inlets Rate - Outlets Leak Rate

For pipes and cisterns where leaks drain volume.

Worked Step-by-Step Examples

Example 1: A can complete a project in 20 days and B can finish it in 30 days. They work together for 5 days, after which A leaves due to illness. In how many more days will B finish the remaining work alone?
Step-by-Step Mathematical Derivation:
•Total Work = LCM(20, 30) = 60 units.
•A's rate = 60 / 20 = 3 units/day. B's rate = 60 / 30 = 2 units/day.
•Combined rate (A + B) = 3 + 2 = 5 units/day.
•Work done in first 5 days together = 5 days × 5 units/day = 25 units.
•Remaining work = 60 - 25 = 35 units.
•Days required by B alone = Remaining work / B's rate = 35 / 2 = 17.5 days.
Answer: 17.5 additional days
💡 Speed Shortcut: Check whether the question asks for "total days" (5 + 17.5 = 22.5) or "more days for remaining work" (17.5).

Common Exam Traps to Avoid

  • ✕Adding days directly (e.g. 20 + 30 = 50 days) instead of combining daily rates.
  • ✕Forgetting that a leak or outlet pipe possesses a negative efficiency.
  • ✕Misinterpreting "A is twice as fast as B" — this means A takes half the time of B.

Interactive Practice Drill (3 Questions)

Instant Explanations • Timed
Assessment Simulator

Time, Work & Pipes/Cisterns Practice Drill

3 Questions • No negative marking
15:00
1Time, Work & Pipes/Cisterns
easy
A can do a piece of work in 12 days, and B can do it in 24 days. Working together, in how many days can they complete the same work?

Question Palette

0 / 3 Answered
Answered (0)
Marked for Review (0)
Unvisited (3)